==Strawman Milestones==
===Notes===
* [B],[M],[E] - denote beginning, middle and end of month
* 'Release' in March, April, May, and June denote an in-progress release.  This is used to get feedback from a small group of interested users, to help steer UI and feature design.
{| cellpadding="2" cellspacing="4" style="backround:#efefef"
{| cellpadding="2" cellspacing="4" style="backround:#efefef"
|-
|-
! colspan="4" style="background:#abcdef" align="center" | Q2 FY06
! colspan="3" style="background:#abcdef" align="center" | Q2 FY06
! colspan="3" style="background:#abcdef" align="center" | Q3 FY06
|-
|-
! style="background:#abcdef" width="80" | March
! style="background:#abcdef" width="80" | April
! style="background:#abcdef" width="80" | May
! style="background:#abcdef" width="80" | June
|-
|-
 
! style="background:#abcdef" width="80" align="center" |
! style="background:#abcdef" width="80" align="center" |
! style="background:#abcdef" width="80" align="center" | March
! style="background:#abcdef" width="80" align="center" | April
! style="background:#abcdef" width="80" align="center" | May
! style="background:#abcdef" width="80" align="center" | June
|-
|-
|
|
|
* [B] Start
* [B] ParaView 2.4.3 Release
* [E] Release
|
* [E] Release
|
* [E] Release
|
* [E] Feature Complete
* [E] Release
|-
|-
! colspan="3" style="background:#abcdef" align="center" | Q4 FY06
! colspan="3" style="background:#abcdef" align="center" | Q1 FY07
|-
|-
! style="background:#abcdef" width="80" align="center" | July
! style="background:#abcdef" width="80" align="center" | Aug
! style="background:#abcdef" width="80" align="center" | Sept
! style="background:#abcdef" width="80" align="center" | Oct
! style="background:#abcdef" width="80" align="center" | Nov
! style="background:#abcdef" width="80" align="center" | Dec
|-
|
* User Testing
* Bi-weekly release
* [M] ParaView 2.6 Release
** ParaView development freeze
|
* User Testing
* Bi-weekly release
|
* [B] Code Freeze
* [E] Beta Release
|
* [B] Beta Testing (small group)
* Quick-turnaround bug fixes
|
* [B] V1.0 Release (Sandia and world)
|
|-
! colspan="3" style="background:#abcdef" align="center" | Q3 FY06
|-
|-
! style="background:#abcdef" width="80" align="center" | Jan
! style="background:#abcdef" width="80" align="center" | Feb
! style="background:#abcdef" width="80" align="center" | March
|-
|-
|
|
|
* Sandia Full Release
** Training (2 sessions)
* ParaView 2.6 remains distributed, use is phased out
|-
|}
|}

Latest revision as of 13:16, 16 February 2006

Strawman Milestones

Notes

  • [B],[M],[E] - denote beginning, middle and end of month
  • 'Release' in March, April, May, and June denote an in-progress release. This is used to get feedback from a small group of interested users, to help steer UI and feature design.


Q2 FY06 Q3 FY06
March April May June
  • [B] Start
  • [B] ParaView 2.4.3 Release
  • [E] Release
  • [E] Release
  • [E] Release
  • [E] Feature Complete
  • [E] Release
Q4 FY06 Q1 FY07
July Aug Sept Oct Nov Dec
  • User Testing
  • Bi-weekly release
  • [M] ParaView 2.6 Release
    • ParaView development freeze
  • User Testing
  • Bi-weekly release
  • [B] Code Freeze
  • [E] Beta Release
  • [B] Beta Testing (small group)
  • Quick-turnaround bug fixes
  • [B] V1.0 Release (Sandia and world)
Q3 FY06
Jan Feb March
  • Sandia Full Release
    • Training (2 sessions)
  • ParaView 2.6 remains distributed, use is phased out