Development Schedule: Difference between revisions

From ParaQ Wiki
Jump to navigationJump to search
No edit summary
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
==Strawman Milestones==
===Notes===
* [B],[M],[E] - denote beginning, middle and end of month
* 'Release' in March, April, May, and June denote an in-progress release.  This is used to get feedback from a small group of interested users, to help steer UI and feature design.
{| cellpadding="2" cellspacing="4" style="backround:#efefef"
{| cellpadding="2" cellspacing="4" style="backround:#efefef"
|-
|-
Line 17: Line 24:
|  
|  
* [B] Start
* [B] Start
* [B] ParaView 2.4.3 Release
* [E] Release
* [E] Release
|
|
Line 41: Line 49:
* User Testing
* User Testing
* Bi-weekly release
* Bi-weekly release
* [M] ParaView 2.6 Release
** ParaView development freeze
|
|
* User Testing
* User Testing
Line 49: Line 59:
|
|
* [B] Beta Testing (small group)
* [B] Beta Testing (small group)
* Quick-turnaround bug fixes
|
|
* [B] V1.0 Release (Sandia and world)
* [B] V1.0 Release (Sandia and world)
Line 59: Line 70:
! style="background:#abcdef" width="80" align="center" | Feb
! style="background:#abcdef" width="80" align="center" | Feb
! style="background:#abcdef" width="80" align="center" | March
! style="background:#abcdef" width="80" align="center" | March
|-
|-
|
|
|
* Sandia Full Release
** Training (2 sessions)
* ParaView 2.6 remains distributed, use is phased out
|-
|-
|}
|}

Latest revision as of 13:16, 16 February 2006

Strawman Milestones

Notes

  • [B],[M],[E] - denote beginning, middle and end of month
  • 'Release' in March, April, May, and June denote an in-progress release. This is used to get feedback from a small group of interested users, to help steer UI and feature design.


Q2 FY06 Q3 FY06
March April May June
  • [B] Start
  • [B] ParaView 2.4.3 Release
  • [E] Release
  • [E] Release
  • [E] Release
  • [E] Feature Complete
  • [E] Release
Q4 FY06 Q1 FY07
July Aug Sept Oct Nov Dec
  • User Testing
  • Bi-weekly release
  • [M] ParaView 2.6 Release
    • ParaView development freeze
  • User Testing
  • Bi-weekly release
  • [B] Code Freeze
  • [E] Beta Release
  • [B] Beta Testing (small group)
  • Quick-turnaround bug fixes
  • [B] V1.0 Release (Sandia and world)
Q3 FY06
Jan Feb March
  • Sandia Full Release
    • Training (2 sessions)
  • ParaView 2.6 remains distributed, use is phased out