ParaView 3 Telecon 08/14/2007
Item | People | Description |
---|---|---|
1 | All | ParaView 3.2 Deliverables/Monthly Build Goals |
2 | All | Feature Freeze |
3 | Moreland | default_servers.pvsc location |
July Build Goals
Multiblock Client Delivery (Dave D)
It is as good as it's going to get for PV 3.2.
Animation GUI Panel (Clint)
Utkarsh put in code to make animation time different from pipeline time. Should be done this week.
Switch to new Exodus reader (Eric)
Cleaning up the panel still needs to be done.
Exodus writer (Eric)
Right now, everything gets mashed into a single exodus block. This will probably remain until exodus multiblock support is complete.
August Build Goals
Clean up memory issues (Amy)
Amy is on vacation. We will add a bug for this.
Multiblock inspector (Dave D.)
Punt. Will be in 3.4. We ran out of time.
Volume render blocks of multiblock data (Dave D.)
Punt. Will be in 3.4. We ran out of time.
Chart vector support (Mark)
Not started.
Misc lookmarks (Eric)
No progress.
Frustum selection (Dave D.)
That should be done in a couple of a days or by the end of this week.
Fast temporal plots (Eric)
Only thing left to do is to test it in parallel.
Global exodus variable (Eric)
Almost ready to check in. Right now the variables are displayed in the exodus panel. The plotting supports the global variables.
Remaining chart features (Mark)
(Includes context menu interactivity)
Should be checking these in today.