ParaView 3 Telecon 05/22/2007
Item | People | Description |
---|---|---|
1 | All | ParaView 3.2 Deliverables Progress |
2 | All | Open level 4 bugs |
3 | Moreland | Resolved bugs |
4 | Moreland | Animation GUI |
5 | All | Summit Prep |
Deliverables
Testing (Clint/Amy/Shawn)
Clint: I'm still working on increasing coverage. And fixing bugs and build issues in 3.0 between coverage results. We're up to about 55% from about 48%. On the GUI side, coverage is lacking for new GUI code, Chart code, and a few other minor features. I plan to cover the Chart code with C++ unit tests. I could wrap up the GUI side this week. There are a significant number of non-GUI classes without coverage that keep the percentage low. What percentage are we shooting for? ParaView 2 has about 58%.
Display Rearchitecture (Utkarsh)
Still ongoing.
Multiblock (Dave D.)
Dave is on travel.
Exodus (Eric)
Started a Wiki page on fast-path temporal plotting option.
Working on the Exodus writer to be able to write all time steps.
Animation (Clint/Utkarsh)
Not started.
Selection (Dave D.)
Dave is still on travel.
Annotation (Yumin)
Yumin is working with Utkarsh on the representation/view stuff.
Spreadsheet View (Utkarsh/Berk)
Probably will not be started until the representation/view rearchitecture.
Charts (Mark)
Mark is still not in.
Support for Multiple Output (Berk)
Berk spent 1 hour on it. Ongoing.
Summit
- Go over software methodology to make sure we are on track.